July 4, 2019
Slovak contractors Vahostav-SK and TuCon will build the first stage of the 4.3km northern bypass in Presov on the R4 dual carriageway.
The contract was awarded in an open tender by Slovakia’s motorway company NDS.
The consortium offered the lowest price of just under €143 million against around €170 million as estimated by NDS which says work will start this summer.
NDS also said that it had received five firm bids for the work which will likely take three years and nine months, for completion in 2